Last updated April 1, 2026
Proposed power plant projects that the Power Plant Research Program (PPRP) is currently reviewing are listed below. Some of these are new facilities and some are modifications to existing facilities, or license modifications to power plants that are already under construction. Projects are grouped together by county location.
The Maryland Public Service Commission (PSC) Case Number refers to the docket number that has been assigned by the PSC. All documents filed with the PSC are available at its website
www.psc.state.md.us. Links to specific documents are included in the project descriptions below.
ALLEGANY COUNTY
Solar Star Allegany South LLC (PSC Case 9805): Proposed 4.95 MW solar array; facility footprint is approximately 22 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item # 22).
- The first public comment hearing was held virtually on January 28, 2026.
- The second public comment hearing will be held the week of May 25, 2026.
Spring Haven Road Solar 1, LLC (PSC Case 9819); Proposed 5.0 MW solar array; facility footprint is approximately 22 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #21).
- A public comment hearing will be held the week of October 26, 2026.
Allegany PV, LLC (PSC Case 9842); Proposed 5 MW solar array; facility footprint is approximately 39 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1)
- The established current procedural schedule is available in the PSC Case Jacket (Item #21).
- A public comment hearing will be held the week of January 11, 2027.
LSE Ino, LLC (PSC Case 9856); Proposed 5 MW solar array (Parrot Eyes Land SE Solar); facility footprint is approximately 23 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1)
- The procedural schedule has not yet been established.
ANNE ARUNDEL COUNTY
Old Island Solar LLC (PSC Case 9854): Proposed 3.9 MW Solar array: facility footprint is approximately 16 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
BALTIMORE COUNTY
Green Road MD PV, LLC (PSC Case 9840): Proposed 2.75 MW Solar array: facility footprint is approximately 36 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #14).
- A public comment hearing will be held the week of March 22, 2027.
CAROLINE COUNTY
ICFTS MD Solar, LLC (Denton Pine Solar) (PSC Case 9835): Proposed 4.63 MW solar array; facility footprint is approximately 47 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #17).
- A public comment hearing will be held the week of November 9, 2026.
CARROLL COUNTY
Chaberton Solar Sunshine LLC (PSC Case 9735): Proposed 3 MW solar array; facility footprint is approximately 17 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #75)
- The first public comment hearing was held virtually on November 13, 2024.
- The second public comment hearing was held on April 8, 2025.
- A third public comment hearing was held virtually on June 5, 2025.
- The case is currently under appeal.
Spring Valley Solar 1 LLC (PSC Case 9736): Proposed 2.25 MW solar array; facility footprint is approximately 14 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #48)
- The first public comment hearing was held virtually on September 25, 2024.
- The second public comment hearing was held January 9, 2025.
- A proposed order granting the CPCN was issued on May 7, 2025 (Item #75)
- The case is currently under appeal.
Cape Horn Road Solar, LLC (PSC Case 9815) – Proposed 4 MW solar array; facility footprint is approximately 17.71 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #17).
- An initial informational public meeting will be scheduled before March 27, 2026.
- A public comment hearing will be held on July 27, 2026.
Hemlock Lane Solar 1, LLC (PSC Case 9824): Proposed 4.0 MW solar array; facility footprint is approximately 27.1 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #23).
- A public comment hearing will be held the week of November 16, 2026.
Eckard Road Solar, LLC (PSC Case 9821) – Proposed 3.0 MW solar array; facility footprint is approximately 25.6 acres
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #18).
- A public comment hearing will be held the week of December 7, 2026.
Chaberton Solar Lambs Knoll LLC (PSC Case 9828): Proposed 5.0 MW solar array; facility footprint is approximately 19 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #20).
- A public comment hearing will be held the week of January 25, 2027.
Benson Road Solar 1, LLC (PSC Case 9843): Proposed 3 MW solar array; facility footprint is approximately 27 acres.
-
The PSC Case Jacket
- The CPCN Application is available iin the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #18).
Carroll Providence Solar 1 and 2, LLC (PSC Case 9858): Proposed 10 MW solar array; facility footprint is approximately 63 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
CECIL COUNTY
Halo NE2 LLC (PSC Case 9776): Proposed 4 MW solar array (Philipe Solar Project); facility footprint is approximately 18 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The current procedural schedule is available in the PSC Case Jacket (Item #51).
- The CPCN Application and amended application is available in the PSC Case Jacket (Item #1).
- An amended application is available in the PSC Case Jacket (Item #45).
- The first public comment hearing was held on June 24, 2025.
- The second public comment hearing was held on March 16, 2026.
Halo NE1, LLC (PSC Case 9779): Proposed 3.45 MW solar array (Wheatly Solar Project); facility footprint is approximately 19.8 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- An amended application is available in the PSC Case Jacket (Item #47).
- The first public comment hearing was held virtually on June 30, 2025.
- The current procedural schedule is available in the PSC Case Jacket (Item #54).
- The second public comment hearing was held on February 25, 2026.
Bouchelle Road Solar 1, LLC (PSC Case 9797): Proposed 5.0 MW solar array; facility footprint is approximately 27.1 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #22).
- The first public comment hearing was held virtually on December 16, 2025.
- The second public comment hearing will be held on April 30, 2026.
TPE MD CE59, LLC (PSC Case 9838): Proposed 3 MW solar array; facility footprint is approximately 18 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #17).
- A public comment hearing will be held the week of February 8, 2027.
LSE Circe, LLC (Case 9839): Proposed 2.85 MW solar array (Ridge Road Solar); facility footprint is approximately 18 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #19)
- A public comment hearing will be held the week of February 22, 2027.
Simpers Road, LLC (Case 9844): Proposed 3.875 MW solar array; facility footprint is approximately 16 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #18).
- A public comment hearing will be held the week of June 14, 2027.
TPE MD CE166 (PSC Case 9845): Proposed 4.99 MW solar array; facility footprint is approximately 28 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #17).
- A public comment hearing will be held the week of May 17, 2027.
North Telegraph Road Solar 1, LLC (PSC Case 9851): Proposed 5.0 MW solar array; facility footprint is approximately 39 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
LSE Aurora LLC (PSC Case 9852): Proposed 5.0 MW solar array; facility footprint is approximately 18 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
Halo JM LLC (PSC Case 9853) Proposed 5.0 MW solar array (State Line Solar); facility footprint is approximately 19 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
OneEnergy Development, LLC (PSC Case 9860) Proposed 5.0 MW solar array (Rising Sun Solar); facility footprint is approximately 27 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
TPE MD CE132A, LLC (PSC Case 9864) Two proposed co-located solar arrays totalling 4.99 MW; facility footprint is approximately 30 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
DORCHESTER COUNTY
Blue Crab Solar & Storage LLC, (PSC Case 9782): Proposed 100 MW solar array, 25 MW battery storage system and operations and maintenance facility on approximately 820 acres. The proposed project also includes a 69 kV Transmission Line.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #25).
- An informational meeting will be held virtually on February 18, 2026.
- A public comment hearing will be held on August 31, 2026.
LSE Iris I, II, and III, LLC (PSC Case 9861): Three proposed co-located solar arrays (Gypsy Hill Road 1, 2, and 3 Solar) totalling 15 MW; facility footprint is approximately 112 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
FREDERICK COUNTY
Black Mills Road Solar 1, LLC (PSC Case 9804): Proposed 5 MW solar array; facility footprint is approximately 46.75 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #23).
- An initial public information hearing was held virtually on January 27, 2026.
- A public comment hearing will be held on June 1, 2026.
Bessie Clemson Road Solar, LLC (PSC 9814): Proposed 5.0 MW solar array; facility footprint is approximately 47.3 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #20).
- An initial public information hearing was held virtually on February 23, 2026.
- A public comment hearing will be held on July 22, 2026.
Opossumtown Pike Solar 1 (PSC Case 9855): Proposed 5 MW solar array; facility footprint is 25.8 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
GARRETT COUNTY
Bloomington Hill 1, LLC (PSC Case 9812): Proposed 5 MW solar array; facility footprint is approximately 49 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #24).
- An initial public information public hearing was held virtually on March 3, 2026.
- A public comment hearing will be held on August 10, 2026.
Bittinger Solar Partnership, LLC (PSC Case 9859): Proposed 5 MW solar array; facility footprint is approximately 49 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.).
Bretheren Church Road 2, LLC (PSC Case 9862); Proposed 2 MW solar array; facility footprint is approximately 23 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.).
LSE Octen LLC Trundles Farm Solar (PSC Case 9867); Proposed 5 MW solar array; facility footprint is approximately 35 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.).
HARFORD COUNTY
Solar Star Dorothy Avenue, LLC (PSC Case 9794): Proposed 5 MW solar array ; facility footprint is approximately 24 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #19).
- The first public comment hearing was held virtually on December 9, 2025.
- The second public comment hearing was held on March 26, 2026.
One Energy Development, LLC, Skipper Solar Project (PSC Case 9796); Proposed 3 MW solar array; facility footprint is approximately 12 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available on the PSC website (Item #23)
- The first public comment hearing was held virtually on December 15, 2025.
- The second public comment hearing will be held the week of May 4, 2026.
Harford Calvary Solar 1, LLC (PSC Case 9816); Proposed 2.5 MW solar array; facility footprint is approximately 11.69 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #31).
- An initial public information hearing was held virtually on February 17, 2026.
- A public comment hearing will be held the week of August 13, 2026.
Hopewell Ranch Solar 1, LLC (PSC Case 9811); Proposed 2.5 MW solar array; facility footprint is approximately 14 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #15).
- An initial public information hearing was held virtually on February 19, 2026.
- A public comment hearing will be held on July 13, 2026.
Harfort Chapel Solar, LLC (PSC Case 9829); Proposed 5.0 MW solar array; facility footprint is approximately 16.7 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #17).
- A public comment hearing will be held on October 6, 2026.
Chaberton Solar Peters Holding, LLC (PSC Case 9847): Two proposed co-located solar arrays totaling 10 MW; facility footprint is 78 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #19)
- A public comment hearing will be held the week of October 26, 2026.
Norrisville Road MD PV LLC (PSC Case 9869): Proposed 3.5 MW solar array; facility footprint is approximately 18 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
KENT COUNTY
Halo Betterton, LLC (PSC Case 9786): Proposed 5 MW solar array (Betterton Solar Project): facility footprint is approximately 18 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1)
- The procedural schedule is currently stayed.
- The first public comment hearing was held virtually on September 9, 2025.
- The project is currently under appeal.
Halo Rock Hall, LLC (PSC Case 9792): Proposed 3 MW solar array : facility footprint is approximately 17.6 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1)
- The procedural schedule has not been established.
TPE MD KE77, LLC (Kennedyville Solar Project); (PSC Case 9799): Proposed 5.0 MW solar array; facility footprint is approximately 52.9 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1)
- The current procedural schedule is available in the PSC Case Jacket (Item #16).
- The first public comment hearing was held virtually on December 5, 2025.
- The Second public comment hearing will be held on April 16, 2026.
Herman Highway Solar 1, LLC (PSC Case 9817); Proposed 3 MW solar array; facility footprint is approximately 29 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #23).
- Two informational community meetings were held on March 10 and 11, 2026
- A public comment hearing will be held the week of October 12, 2026.
MD American Kestrel, LLC (PSC Case 9823): Proposed 5.0 MW solar array; facility footprint is approximately 39.43 acres.
-
The Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #19).
- A public comment hearing will be held the week of September 7, 2026.
Shadding Ranch Road, LLC (PSC Case 9846): Proposed 4.5 MW solar array; facility footprint is approximately 28 acres.
-
The PSC Case Jacket
- The CPCN application is available in the PSC Case Jacket (Item #1)
- The current procedural schedule is available in the PSC Case Jacket (Item #25).
- A public comment hearing will be held the week of June 28, 2026.
OneEnergy Development, LLC (PSC Case 9863: Proposed 4 MW solar array, facility footprint is Approximately 23 acres.
- The PSC Case Jacket
- The CPCN application is available in the PSC Case Jacket (Item #1)
- The procedural schedule has not yet been established.
MONTGOMERY COUNTY
Chaberton Solar Ramiere, LLC (PSC Case 9733): Proposed 3 MW solar array; facility footprint is approximately 11 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item# 84).
- The first public comment hearing was held the week of August 22, 2024.
- The second public comment hearing was held on April 14, 2025.
- A third public comment hearing was held on May 19, 2025.
- The case is currently under appeal.
PRINCE GEORGE’S COUNTY
Vermillion Solar, LLC (PSC Case 9793): Proposed 3 MW solar array; facility footprint is approximately 20.19 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #37).
- The first public comment hearing was held on October 1, 2025.
- The second public comment hearing was held on January 22, 2026.
- A Proposed Order granting the CPCN was issued on March 24, 2026 (Item #46).
Croom Road Solar (PSC Case 9837): Proposed 3 MW solar array: facility footprint is approximately 17 acres.
-
The PSC Case Jacket
- The CPCN application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #18).
- A public comment hearing will be held the week of May 3, 2027.
QUEEN ANNE’S COUNTY
Soltage MD DevCo, LLC And Berlin Living, LLC (PSC Case 9826): Application for 6 co- located solar arrays totaling 18 MW; facility footprint is approximately 112.84 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #15).
- A public comment hearing will be held on June 22, 2026.
LSE Aquarius, LLC (PSC Case 9827): Proposed 2.988 MW solar array (Kent Point Solar); facility footprint is approximately 10.85 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #18).
- A public comment hearing will be held on January 5 or 6, 2026.
Chaberton Solar Hayford, LLC. (PSC 9834): Proposed 4.0 MW solar array; facility footprint is approximately 14 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #19).
- A public comment hearing will be held the week of November 30, 2026.
TPE MD QA15A, LLC (PSC Case 9868): 3 proposed co-located solar arrays totalling 9.98 MW; facility footprint is approximately
- The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
SOMERSET COUNTY
Old Princess Anne Community Energy Initiative, LLC (PSC Case 9822): Proposed 2.25 MW Solar array; facility footprint is approximately 15.3 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule is available in the PSC Case Jacket (Item #17).
- An informational public meeting will be held prior to March 31, 2026.
- A public comment hearing will be held on August 24, 2026.
TALBOT COUNTY
Halo Cordova, LLC. (PSC Case 9789): Proposed 4.0 MW solar array (Highfield Creek Solar Project); facility footprint is approximately 17.2 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #1833).
- The first public comment hearing was held virtually on September 24, 2025.
- The second public comment hearing was held on January 29, 2026.
- A Proposed Order granting the CPCN was issued on March 13, 2026.
WASHINGTON COUNTY
Resh Road Solar 2, LLC (PSC Case 9831): Proposed 4.25 MW solar array; facility footprint is approximately 15 acres.
- Project Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #22).
- A public comment hearing will be held the week of January 11, 2027.
WICOMICO COUNTY
Wicomico Rayne Solar, LLC, (PSC Case #9795); Proposed 5.0 MW solar array; facility footprint is approximately 37 acres.
-
The Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #21).
- The first public comment hearing was held virtually on December 3, 2025.
- The second public comment hearing will be held on April 2, 2026.
Nanticoke Road Solar 2, LLC (PSC Case #9806: Proposed 5.0 MW solar array; facility footprint is approximately 33 acres.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available on the PSC website (Item #19).
- The first public comment hearing was held virtually on January 7, 2026.
- The second public comment hearing will be held on May 14, 2026.
Kumquat & Citron Cleantech, LLC (Citron Solar) (PSC Case 9694): Proposed 7.20 MW solar array; facility footprint is approximately 24 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket
- The current procedural schedule is available in the PSC Case Jacket (Item #34).
- The first public comment hearing was held on July 10, 2023.
- The second public comment hearing will be held on September 7, 2026.
WORCESTER COUNTY
Woodside Solar 1, LLC (PSC Case #9825): Proposed 5.0 MW solar array; facility footprint is approximately 23 acres.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #16).
- A public comment hearing will be held the week of September 14, 2026.
TRANSMISSION LINE PROJECTS
BGE –Brandon Shores Retirement Mitigation Project (PSC Case 9748): Construction of a group of projects that are needed to maintain the electric system reliability following the retirement of the Brandon Shores Generating Station. The Project extends approximately 2.2 miles from the Maryland-Pennsylvania (MD-PA) State line to the Graceton Substation. From the Graceton substation in Harford County, the Project extends 29 miles to the proposed Batavia Substation in Baltimore County. From the proposed Batavia Substation, the Project is proposed to extend an additional 6 miles to the existing Riverside Substation. Additional project work is proposed to occur on the proposed Solley Road Substation in Anne Arundel County.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item# 96)
- A public comment hearing was held on April 9, 2025.
- A second public comment hearing was held on April 10, 2025.
- A third public comment hearing was held on April 23, 2025.
- A proposed order granting the CPCN was issued on March 13, 2026.
PSEG Renewable Transmission LLC – Maryland Piedmont Reliability Project (PSC Case 9773): Construction of a new 500kv single circuit overhead transmission line. The line extends approximately 67 miles across portions of Baltimore, Carroll and Frederick Counties from the existing Doubs Substation to west of the existing Conastone Substation.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #638).
- Public comment hearings will be held in each county occupied by the project during the weeks of September 21 and September 28, 2026.
Potomac Edison – Carroll-Hunterstown Improvements (PSC Case 9803): Rebuilding an existing single circuit 138 kV transmission line to 230 kV standards, with both a 138 kV circuit and a 230 kV circuit. The line extends approximately 24 miles from the Carroll Substation in Carroll County, Maryland to the Hunterstown Substation in Pennsylvania. Approximately 11.3 miles of the project is located in Carroll County, Maryland.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The current procedural schedule is available in the PSC Case Jacket (Item #13).
- An evening public comment hearing will be held virtually the week of July 27, 2026.
Potomac Edison – Messick Road-Ridgely Road 138 kV Transmission Line Rebuild (PSC Case 9818: Rebuilding an existing single circuited 138 kV transmission line. The line extends approximately 4 miles from Mineral County, West Virginia to Allegany County, Maryland. Approximately 2.0 miles of the project is in Allegany County.
-
Project Case Summary
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule is available in the PSC Case Jacket (Item No. 11).
- The date for the public comment hearing has not yet been established.
NextEra Energy Transmission Mid Atlantic, Inc. – 500 kV transmission line associated with the MidAtlantic Resiliency Link Project (PSC Case 9857): Proposed new transmission line in Allegany and Garrett Counties. Approximately 35 miles of the transmission line will be located within Maryland.
-
The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
Potomac Edison – Gore-Doubs-Goose Creek Improvements Project (PSC Case #9870) – Proposal to make multiple modifications within an existing transmission line right of way, including the addition of two new 500 kV transmission lines.. The Project extends approximately 18 miles in Frederick and Montgomery Counties.
- The PSC Case Jacket
- The CPCN Application is available in the PSC Case Jacket (Item #1).
- The procedural schedule has not yet been established.
Archived Projects