SUMMARY OF THE 2ND
MEETING OF THE
DNR ARTIFICIAL
REEF COMMITTEE (ARC)
TAWES STATE OFFICE
BUILDING, C-1, ANNAPOLIS, MD
TUESDAY, July 24,
2007, 6 PM-9PM
Prepared by Erik
R. Zlokovitz
Fisheries
Biologist, MD DNR-Fisheries Service
START OF MEETING/LIST OF ATTENDEES:
Marty Gary of MDDNR convened the 2nd meeting of the MDDNR Artificial Reef Committee (ARC) at 6pm on 7/24/07 in the C-1 Conference room, Tawes State Office building, Annapolis, MD. Members of the ARC and proxies in attendance included:
-Marty Gary, MD DNR Liaison
-Erik Zlokovitz, MD DNR Liaison
-Kent Carlson, Private Citizen
-Bill Goldsborough, CBF
-Terry McGean, Town of Ocean City (Proxy for Gail Blazer)
-Captain Mark Galasso, Chesapeake Guides Association
-Ed Liccione, CCA
-Dolden Moore, BPW
-Capt. Greg Madjeski, MCBA
-Capt. Marty Simounet, MCBA
-Gary Setzer, MDE
-Bill Huppert, MSSA
-C.D. Dollar, Outdoor Writers/The Fisherman Magazine
-Rich Takacs, NOAA-Restoration Center
-Capt. Bruno Vasta, Solomons Charter Captain Association and CBARC
-Capt. Rick Younger, MD DNR Liaison/MGS
-Brandon Ghrist, MES (Proxy for Tom Humbles)
-Capt. Curtis Johns, Tangier Sound and Lower Eastern Shore Charter Boats
-Capt. Dicky Webster, Tangier Sound Charter Boats
-David Dansberger, SFAC
Others in attendance included:
-Mike Baker, Environmental Manager, Woodrow Wilson Bridge Project
-Clint Waters, MSSA
-Bob Geisler, MSSA
-Andrew Loftus, Andy Loftus Consulting
-Todd Chason, on behalf of Honeywell Corp.
-Steph McReynolds, CBF
INTRODUCTION/GREETINGS/ANNOUNCMENTS:
Marty Gary noted that Rick Younger and Jeff Halka were added to the list of ARC/DNR liaisons, because of their technical expertise and survey work with MGS, including operation of the DNR/MGS research vessel (R/V Kerhin).
Marty noted that Barge #9 from the Woodrow Wilson Bridge Project had been deployed on 7/9/07 at the lower Tangier Sound Reef site (near Fox Is. Buoy, off Crisfield). This was the first deployment of material from the WW Bridge project at this reef site. The operation was conducted with support from Capt. Curtis Johns. An “Appendix A” planning document from the MD Reef plan was filled out for this site. The reef material was set on an edge on hard bottom, where water depths drop from roughly 20 feet down to 40 feet. This first deployment at Tangier used 1100 tons of material, and created a row cross-tide (perpendicular to current) approximately 50-60 feet long, with vertical relief as high as 4 feet in some areas. The main purpose of this deployment was to build a hard-base for reef material at Tangier.
The remaining MARI funding balance at the date of this meeting (7/24/07) was $3,000 after payment for barges 2-8 from the Woodrow Wilson Bridge Project. Cost for each barge from #2-8 ranged from $7,000-$52,000, with unit cost of material ranging from $20.00-$22.50 per ton.
A ceremony recognizing the contribution of money from Dominion LNG for a reef building project is planned for late summer of 2007. The Governor of MD would be invited to this event. Funds from Dominion would be slated for a new proposed reef site at the “Gooses” fishing grounds in middle Chesapeake Bay.
According to Mike Baker of the WW Bridge Project, the reef site under construction at Pt. No Point is approximately 50% done. The target/goal of 10 feet of vertical relief has been reached in many sections of the reef.
Maryland has requested 600 retired subway cars from NYC for deployment off the coast of Ocean City, MD. This operation has been bumped back from August, 2007 to late-September, 2007 at the earliest, due to logistical issues. Maryland is at the top of the priority list to receive subway cars for reef construction. However, the southernmost states along the east coast, such as South Carolina, would get delivery first. EPA region 3 (Philadelphia office) predicted the life span of these cars to be approximately 40 years. Concerns about asbestos are minimal, since the relatively small amounts of asbestos in the cars are encapsulated in a hard epoxy.
Steph McReynolds of CBF announced an open house/tour of the CBF oyster restoration facility in Shady Side. This event was designed to inform the public about oyster restoration efforts in the Bay.
Honeywell Branding Exercise:
Todd Chason spoke on behalf of Honeywell Corp. and discussed the company’s intention to conduct a branding exercise on a reef deployment operation in the lower Chesapeake Bay. The company has given money to the MARI funds and wants to promote reef activities in a shore and water-based event. They plan to place a banner on a barge with reef materials and also hold a shore based event, most likely in Solomons.
Vote for Chairman of the ARC:
Large amounts of post-blast concrete rubble material ranging from gravel up to boulder size pieces, but averaging 12-15 inches in diameter, have settled on the Potomac Riverbed and must be clamshelled off the bottom and loaded onto barges, after mud has been sifted out. The operation deals with various difficulties. First of all, the operation on the River must be finished by February 2008, due to conflicts with endangered shortnose sturgeon migrations, and other anadromous fish issues. Torches must be used to burn off rebar protruding from rubble and asphalt must be milled off.
In some spots on the Point No Point Reef, 5-8 feet of vertical relief are visible. The reef base was built in about 32 feet of water, and the top of the reef is now up to about 25 feet in some places.
Projections of reef deployments from WW Bridge project:
Mike Baker noted that August would be a very busy month for reef deployments from the WW bridge project. He projected 2-4 bargeloads would be ready for the week of July 30th. In theory, 2 loads of deck slabs could go to Tangier to continue building up that reef base and 2 loads of post-blast rubble could go to Pt. No Pt. (PNP), in a one week period. A total of 4 bargeloads of material would be needed to build up the reef at Tangier Sound.
Mike projected that 1-3 bargeloads of material per week may be delivered from the end of July through at least September. Potential deployment sites for this period would be Tangier Sound, Cedar Pt., Little Cove Pt., and PNP. During the fall months and and until mid-February 2008, 1-2 bargeloads will be delivered per week. It is hoped that the PNP reef can be finished during this time, and that a reef base can be started at the proposed Gooses site (after the Gooses site permit process is completed). Each bargeload would typically contain 900-1200 tons of material.
Rich Takacs of NOAA noted that he had access to new side-scan sonar technology which could be used to generate high-res 3-D images of reef profiles. There is an interest in using this technology to judge the progress and status of the single cross-current row of reef material at PNP.
Discussion of Cedar Pt. Site vs. Little Cove Pt. Site and
Honeywell Media Event: