Derelict Gear Retrieval Project Schedule | Maryland DNR Fisheries Service News

Derelict Gear Retrieval Project Schedule

3/19/2012  |   Posted by bkdavis

Tags: Commercial, Blue Crab  
The 2012 Derelict Gear Retrieval Project will begin on Monday March 19, 2012 and continue over a four week period at 14 sites. Below is a list of locations and the scheduled work period for that area. Please note that some locations are scheduled for more than one work period and dates are weather dependent. If you have any questions, please contact the Oyster Recovery Partnership at 410-990-4970.

Click to view maps of locations.

Group

Location

Work Period

1

Patuxent

3/19-3/22

2

Smith Island (Mouth of channel)

3/19-3/22

3

Little Annemessex (Crisfield)

3/19-3/22

4

Big Annemessex (mouth of river)

3/19-3/22

5

Tangier Sound (Nanticoke/Wicomico/DI)

3/19-3/22

6

Lower Hooper Island North (Middle Island)

3/19-3/22

7

Lower Hooper Island South (Lower Island)

3/19-3/22

8

Tangier Sound (Nanticoke/Wicomico/DI)

3/26 3/29

9

Lower Hooper Island North (Middle Island)

3/26 3/29

10

Lower Hooper Island South (Lower Island)

3/26 3/29

11

Severn River

3/26 3/29

12

Rhode / West / South

3/26 3/29

13

Magothy

4/2 4/5

14

Patapsco North Side

4/2 4/5

15

Fairlee Creek

4/2 4/5

16

Hart Miller Island

4/9 4/12

17

Fairlee Creek

4/9 4/12

18

North East

4/16 4/19